AKASHI - Manhours Entry

Get plain text:

curl -H "Accept: text/plain" https://jugoya.ai/guides/akashi/manhours

Overview

Enter work hours by project and task in AKASHI. Covers month selection, project/task hierarchy, time entry, and managing multiple projects per day.

URLs

PageURLPurpose
Manhourshttps://atnd-awj.ak4.jp/ja/manhoursWork hours entry page

Critical Constraints

  • Project/Task Hierarchy: Must select project first, then task within that project
  • Time Format: Enter time in H:MM format (e.g., 8:00, 7:30, 10:00)
  • Element References Change: Take fresh snapshot after each action as refs change

Workflow: Navigate to Manhours

1. Go to Manhours Page

Navigate to https://atnd-awj.ak4.jp/ja/manhours

2. Select Target Month

  1. Click the date input textbox (shows current date range)
  2. A calendar picker appears with years and months
  3. Navigate to the correct year using « and » arrows
  4. Click the target month to load that period's data

Workflow: Enter Manhours for a Date

1. Open Edit Modal

Find the target date row in the table and click 修正 (Edit) button.

2. Select Project

  1. Click the project dropdown (プロジェクトを選択)
  2. Select or search for the target project

3. Select Task

  1. Click タスクを選択 to open task dropdown
  2. Select the appropriate task within the project

4. Enter Time

  1. Find the time input field (shows 0:00)
  2. Enter time in H:MM format
  3. Optionally add a comment

5. Save Entry

Click 確定 (Confirm) button to save.

Workflow: Multiple Projects Same Day

1. Add First Project

Complete the project/task/time entry for the first project.

2. Add Another Project

Click 選択したプロジェクトを追加する (Add Selected Project) to add another row.

3. Repeat Selection

Select project → task → enter time for the second project.

4. Confirm All

Click 確定 (Confirm) to save all entries.

Workflow: Input to Existing Task

When a project/task was previously used, it appears as an existing row:

1. Identify Existing Tasks

After opening edit modal, existing project sections show:

  • Project name header
  • Task rows with time input fields

2. Direct Time Input

  1. Find the existing task row under its project section
  2. Locate the time input textbox (shows 0:00)
  3. Enter time directly without dropdown selection
  4. Click 確定 (Confirm) to save

Key Elements Reference

Element (Japanese)Element (English)Purpose
修正EditOpens edit modal for a date
プロジェクトを選択Select ProjectProject dropdown
タスクを選択Select TaskTask dropdown within project
確定ConfirmSave and close modal
削除DeleteRemove an entry
未入力時間Unallocated TimeRemaining hours to assign
コメントCommentOptional note field

Verification

After saving, verify:

  • Correct time appears under each project column
  • 未入力時間 (Unallocated time) shows 0:00

Troubleshooting

IssueCauseSolution
Task dropdown not appearingProject not selectedSelect project first
Time input not visibleTask not selectedSelect task first
Element refs invalidPage state changedTake fresh snapshot
Unallocated time remainingHours don't match work timeAdd entries until 0:00

Notes

  • Each date can have multiple project/task combinations
  • Total hours should match actual work time for that date
  • Use 削除 (Delete) to remove an entry before confirming
  • Previously used project/task combinations appear as existing rows for faster input